The software projects are considered to be successful if the
cost and the duration are within the estimated ones and the
quality is satisfactory. To attain project success, the project
management, in which the final status of project is estimated,
must be incorporated.
In this paper, we consider estimation of the final status(that
is, successful or unsuccessful) of project by applying Bayesian
classifier to metrics data collected from project. In order to
attain high estimation accuracy rate, we must select only a
set of appropriate metrics to be applied. Here we consider two
selection methods: the first method by the experts and the second
method by the statistical test.
Then we conducted an experiment using 28 project data and 29
metrics data in an organization of a certain company. The result
showed that the method by the test gave higher accuracy rates than
the method by the experts, and Bayesian classifier with the test method is
effective to estimate project success.